Implementation of steel bridge 250 meters long, by the use of steel tension bar, fixed to reinforced concrete and mega steel plates anchored to the land, implementation of paving an expantion joints. Hydrogeologic positioning of the intervention area with river bed correction by construction of new cofferdams with reno mattress and implementation of gabionades.
REALIZZAZIONE DEL PONTE S.P. 248
Operations:
- Excavations and earth moving
- Terrane perforation
- Piling
- Reinforced concrete foundation
- Reinforced concrete Pylons and walls
- Prefabricated floor system
- Paving
- Gabionades
- Hydrogeological work of the area